Yоur teаm is mаnаging the launch оf a new wоod pellet grill as part of JZ's Pellet Project. The launch involves multiple activities, each with varying durations. You need to determine the probability of completing the project within a specific timeframe. The activities and their respective optimistic (a), most likely (m), and pessimistic (b) time estimates (in weeks) are as follows: Activity Predecessor(s) Optimistic (a) Most Likely (m) Pessimistic (b) A - 2 4 6 B A 1 3 5 C A 2 5 8 D B, C 3 6 9 E C 1 2 3 F D, E 2 3 6 What is the probability that the project will be completed within 17 weeks? Report you answer in decimal form to the nearest hundredths place.