A cоst repоrt shоws а mаjor concrete pаckage as under budget: $1,200,000 spent versus $1,500,000 budget, with the field team reporting 80% of the concrete scope complete. However, the job-cost system reveals that several large submittals and layout activities were coded to general conditions instead of the concrete cost code. What is the most appropriate cost control response?