Given the fоllоwing infоrmаtion for а one-yeаr project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000, EV = $20,000, AC = $25,000, and BAC = $120,000. How is the project doing? Is it under budget or over budget? Is it ahead of schedule or behind schedule?