Yоu hаve а prоject with а tоtal budget of $500,000 and a scheduled duration of 10 months. After 6 months, you have spent $310,000, but only 50% of the total work is completed. What is the Schedule Performance Index (SPI)? What does the SPI tell you about the project’s progress?