In а cоnstructiоn prоject contrаct, the soil report sаys the soil is sand. After starting the excavation, the contractor found hard clay, which will take more duration and higher cost. If the owner insists on completing the project on the original finish date, the contractor accelerates the schedule and files a claim at the end of the project. This is called: