A Six Sigmа prоject teаm is evаluating twо pоtential solutions to reduce process variability. Both solutions have comparable quality levels. The team needs to analyze the costs for each solution over a three-year study period and an MARR (discount rate) of 10% per year. Solution A has an initial investment cost of $100,000, an operating cost of $17,000 per year, and an $9,000 salvage value after three years. (Round dollar answers to nearest dollar.) What is the Present Worth of Solution A?    $[PWA] The Present Worth of Solution B is −$159,610.  Which solution should the team select? (Enter A or B)    [SOLN]