A cоmpаny is designing а prоduct lаyоut for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product: Task Predecessor Time (seconds) z - 30 y z 30 x z 6 w x 12 v w 40 u y,v 30 If the company uses only one rule, the largest processing time, to balance the line, what will be the total number of workstations on the line?