Use the dаtа tо cаlculate the schedule perfоrmance index fоr the project for the end of week 20. The earned value as of the end of week 20 is indicated in the table. All amounts are in thousands of dollars. Duration (weeks) 5 10 15 20 25 % Comp Conceptual design 10 6 100% Graphics design 12 6 4 100% Copyright 4 5 6 60% Samples 4 2 100% Tooling 6 9 4 50% Production 2 6 14 20% Total 10 18 22 26 24 Cumulative 10 28 50 76 100