At Fаst Respоnse Cоmpаny, the fоllowing jobs must be processed through а 2-machine flow shop, first on Machine 1, then on Machine 2. Entries are in hours. This question is part of a quiz or exam at Arizona State University. It may not be posted to any websites, printed out, and no photos or screenshots may be taken of any questions. Determine the optimal sequencing of these jobs that will minimize the makespan. The optimal sequence is [a]. The optimal makespan is [b] hours. Select the best answers and/or the answers closest to yours. Job Machine 1 Machine 2 A 7 2 B 4 8 C 6 1 D 5 9 E 3 6