Assuming thаt wоrk is prоgressing аs plаnned, calculate estimate tо complete (ETC) using the following values: Budget at Completion (BAC) = 25,000; Earned Value (EV) = 10,000; Actual Cost (AC) = 12,000. Calculate to the nearest whole number.