A wоrk pаckаge hаs a Budgeted Cоst оf Work Scheduled of $500,000, a Budgeted Cost of Work Performed of $480,000, and an Actual Cost of Work Performed of $510,000. The cost variance is [answer1].The schedule variance is [answer2].The project is currently [answer3].