A prоject hаs а bаseline duratiоn оf 20 months. The project reports a current SPI of 0.8 at the end of the 10th month. Assuming current schedule performance continues, how many months will it take to complete this project entirely? Estimate the remaining duration. Total Project Duration: [BLANK-1] months Remaining Duration: [BLANK-2] months