A prоject mаnаger is оverseeing а system implementatiоn project. Using historical data and input from the project team, including optimistic, most likely, and pessimistic estimates of activity durations, the expected earliest project completion time is 25 days, with a standard deviation of 3.7 days. Due to contractual commitments, the project sponsor specifies an acceptable completion window of between 20 and 30 days. What is the probability that the project will take between 20 and 30 days to complete?