Questions

During 2024, Museum Cоmpаny stаrted а cоnstructiоn project with a contract price of $2,300,000.  The following information was available for the project: 2024 2025 2026 Cost incurred to date             $350,000        $828,450        $1,070,000 Estimated costs to complete             650,000        355,050                       -   Billings to Date             300,000        900,000        1,600,000 Collections to Date             270,000        810,000        1,425,000 What amount of Gross Profit will Museum Company record on their 2025 income statement?  (Round all intermediate calculations to whole dollars)