Aаrоn decides tо hire Sebаstiаn tо build an extension onto his house. They enter into a contract on March 1st, and the deadline for completing the extension is May 1st. Given the nature and size of the project, the extension will take at least one week to complete once the work on it has started. The Aaron-Sebastian contract states that “time is of the essence” because Aaron is having family over from May 2nd to May 12th, and Aaron needs the extra space for them to stay. Even though the deadline gets closer and closer, Sebastian never starts construction. Finally, on April 27th, Aaron declares Sebastian to have breached the contract. Sebastian argues that Aaron cannot declare a breach yet. Who is correct?